UV-CIPP, or Ultraviolet Light-Cured In-Place Pipe Repair Technology


Unsaturated polyesters were the earliest oligomers used in light-curable materials. In 1968, Bayer AG of Germany developed the first-generation light-curable wood coatings, which featured a formulation system composed of unsaturated polyesters and styrene, thereby paving the way for the industrial-scale production of light-curable products. As a manufacturer of light-curable resins, Boxing New Materials would like to take this opportunity today to talk with you about unsaturated polyesters.

Unsaturated polyester is produced by the polycondensation of diols and dicarboxylic acids upon heating. Its molecular chains contain linear or branched polyester macromolecules with reactive C=C double bonds. The diols used include ethylene glycol, propylene glycol, 1,4-butanediol, and others. The dicarboxylic acids must be unsaturated dicarboxylic acids or their anhydrides, such as maleic acid, maleic anhydride, and fumaric acid, which impart unsaturation to the polyester molecules. Furthermore, these unsaturated polyesters are often used in combination with a second type of dicarboxylic acid—such as phthalic acid, isophthalic acid, succinic acid, adipic acid, or adipic anhydride—to tailor the properties of light-curable materials.

Unsaturated polyesters, owing to their readily available raw materials, low cost, and simple synthesis process, when combined with styrene, yield cured coatings that exhibit excellent hardness, solvent resistance, and heat resistance. They also enable the formation of relatively thick, UV-curable coatings, which can produce high-gloss and highly丰满 (full-bodied) decorative effects in wood finishing applications. However, this system suffers from several drawbacks: slow UV curing rate, poor flexibility, inferior yellowing resistance, and weak adhesion to most substrates. Moreover, styrene itself has a strong odor and significant toxicity, and has been classified by the World Health Organization as a Group 2B carcinogen. Currently, unsaturated polyester systems are largely phased out from conventional formulations used in UV coatings, inks, and adhesives, but continue to play an important role in the form of composite materials—for instance, in artificial marble, fiberglass, and UV-CIPP lined flexible pipes.

UV-CIPP, or Ultraviolet-Cured In-Place Pipe Repair Technology, uses a liner hose made of a photo-curable composite material that includes unsaturated polyester. This technology is primarily used for the repair of various drainage pipes, such as sewage pipes and stormwater pipes. It is a trenchless pipe rehabilitation technique whose construction principle involves mechanically pulling a felt-lined hose saturated with photosensitive resin into the pipe to be repaired. Compressed air is then injected to ensure the hose adheres tightly to the inner wall of the pipe. Subsequently, ultraviolet lamps are used to cure the resin inside the pipe, creating a high-strength, resin-lined new pipe that completely lines the entire length of the existing pipe.

The light-cured liner repair hose (referred to as the hose) consists, from inside to outside, of an inner liner, a glass fiber braid impregnated with resin, an outer liner, and an ultraviolet protection film.

Inner liner: The innermost plastic layer of the hose, which protects the resin impregnating the fiberglass braid from volatilization during storage and transportation of the hose, and ensures that the resin is distributed as evenly as possible when the hose is inflated. After the hose has cured, the inner liner must be pulled out from inside the liner tube.

Glass fiber fabric: The main body of the hose, used to absorb the curing adhesive; after curing, it can increase the pipe's strength.

Outer Sheath: The plastic film on the outermost layer of the hose, which protects the resin impregnating the glass fiber braid from volatilization during storage and transportation of the hose, and ensures that the resin is distributed as evenly as possible when the hose is inflated.

Protective film: The outermost plastic layer of the hose, which protects it from ultraviolet radiation and prevents scratches during storage, transportation, and pulling.

Manufacturing process of light-cured liner-repair hoses:

Step 1: The “dry materials” are folded and formed according to the design specifications, ensuring that the glass fiber layer reaches the specified wall thickness. Additionally, the inner membrane, impermeable membrane, and UV-resistant membrane have all been fully installed.

Step 2: Wet-Feed Production—Move the “dry feed” to the automated pre-impregnation line and begin preparatory operations prior to impregnation. First, seal the “dry feed.” Next, perform vacuum treatment and use a mixing and feeding device to inject resin into the liner tube. Then, carry out several rounds of roller pressing and continuous vacuum extraction to ensure the liner tube is completely filled with resin. Following that, inspect the impregnation effect and remove any excess resin. Finally, fold and pack the product into boxes.

So, once the hose is completed, how is it used for pipe rehabilitation? Next, let’s talk about the UV-CIPP repair process.

Before inserting the liner hose, we need to carry out preparatory work, including site surveys, pipeline plugging, diversion, unclogging, and sediment removal. Now let’s get started with the pipeline repair.

First, apply the base film.

Before pulling in the liner hose, a base membrane should be laid inside the existing pipe. The base membrane should be positioned at the bottom of the existing pipe and cover more than one-third of the pipe’s circumference. It should also be securely fastened at both ends of the existing pipe. The base membrane must have sufficient strength to provide adequate protection for the pulled-in liner hose.

Second, insert the inner lining hose.

The liner hose should be smoothly and slowly pulled into the existing pipe along the bottom membrane at the pipe’s base; the pulling speed must not exceed 5 meters per minute. During the process of pulling in the hose, it must not be worn or scratched.

Note: The inner lining hose must not be inverted or twisted inside the pipe.

The two ends of the hose should extend 300–600 mm beyond the original pipe. After the hose is pulled into the original pipe, it is advisable to fold it in half and place it on the bottom membrane.

Third, tie the head bundle, inflate it, and insert it into the lamp holder.

Connect the tracheal tube to the connector and check the tightness of the connector. Before inflating, verify the sealing at each connection point of the tubing.

The inflation process must be carried out strictly according to the inflation requirements provided by the material supplier, gradually inflating in stages until completion. Do not rush through the inflation process.

Fourth, turn on the UV lamp, set the curing speed, and start curing.

During the light-curing process, air pressure should be maintained inside the liner pipe to ensure tight contact between the liner pipe and the existing pipeline.

After the liner pipe has been cured, the pressure inside the pipe should be slowly reduced to atmospheric pressure.

Fifth, after curing is complete, trim off the excess material at both ends, pull out the inner lining, and restore the pipeline’s cross-section.

Use the liner material cutting equipment to cut open the pipe inlet, remove the tie-in head, and pull out the inner liner.

The annular gap between the liner pipe and the existing pipeline needs to be filled with grouting.

The above is the UV-CIPP repair process.